Donabate Post Primary incorporates teaching blocks, library, I.T. facilities, special needs teaching, and an international standard hockey pitch. The school is arranged around a central courtyard and works include all site infrastructure, water treatment plant, landscaping, access road, and car park. It is a fine example of a modern educational facility procured under Design and Build.

Client: P. Elliott Company Ltd

Phase 1:

Start Date: November 2008
Completion: June 2010

Phase 2:

Start Date: January 2011
Completion: Estimated February 2012

Services:

  • Installation of Temporary Piling Mats
  • Soil Stabilisation
  • Capping Replacement

Challenges & Achievements:

This project has proved to be particularly challenging due to the extremely high organic content of the soil on site. Perseverance and adaptation of techniques have allowed us to ensure that budgets are maintained and timescales met. Tackling these unexpected conditions and subsequent completion of Phase 1 resulted in CAB’s tender win for Phase 2.